Project Duration
Stipulated Date of Commencement
July 26 2018
Stipulated Date of Completion /
Likely Date of Completion March 25 2019
Likely Date of Completion March 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,100,310.00
Awarded for
₹ 31,895,244.00
Project highlights
Interior works for Sanjay School building at Vasco & Porvorim which includes new modular furnitures for special childrens, carpentary works, new stage along with acoustics etc.
Contractors
M/s. Macro Enterprises
Consultants
M/s Rajesh Kenkre
See Similar Projects
Interiors and Furniture work.
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Bicholim Taluka – Package F (G.P.S. Kelbaiwada Mayem, G.P.S. Borde, G.P.S. Bhavkai Mayem, G.P.S. Haldonwadi Mayem ).
View Project
Repairs/ Upgradation & Maintenance of Government Primary schools in the State of Goa –Civil, Plumbing & Electrical works (Bardez Taluka) Package I-C:- GPS Sirsaim, GPS Coniwada, GPS Tarawada
View Project