Project Duration
Stipulated Date of Commencement
January 20 2005
Stipulated Date of Completion /
Likely Date of Completion June 06 2005
Likely Date of Completion June 06 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,437,000.00
Awarded for
₹ 1,509,000.00
Project highlights
Upgrading the Martyrs’ Memorial by fixing glass mosaic tiles to the main vertical monument, granite tiles to the horizontal platforms
Contractors
M/s. C. V. Naik
Consultants
M/s. Rahul Deshpande & Associates