Project Duration
Stipulated Date of Commencement
May 08 2006
Stipulated Date of Completion /
Likely Date of Completion August 07 2006
Likely Date of Completion August 07 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,447,398.00
Awarded for
₹ 51,402,737.00
Project highlights
Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, laying pavers wherever required. The approximate length of the road is around 11.8 kms.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Madhav Kamat & Associates