Project Duration
Stipulated Date of Commencement January 30 2014
Stipulated Date of Completion /
Likely Date of Completion
February 13 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 49,979,192.00
Awarded for ₹ 47,708,350.00

Project highlights

Hotmixing of road from District collectorate upto Agalli junction, Fatorda

 
Gallery Image
Contractors
M/s.Ritesh Developers Pvt. Ltd
Gallery Image
Consultants
M/s.Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Improvement and Upgradation of road network at Piligao, Curti, Ponda Town and Chodan.

View Project
Similar Project

Widening of roads and relocation of structures in Fatorda Constituency- Phase I

View Project
Similar Project

Electrification of New Link Road from Gaundali To Khandola

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.