Project Duration
Stipulated Date of Commencement
December 22 2012
Stipulated Date of Completion /
Likely Date of Completion February 21 2013
Likely Date of Completion February 21 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,768,825.00
Awarded for
₹ 2,729,900.00
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Gurudutt Sanzgiri