Project Duration
Stipulated Date of Commencement
April 01 2013
Stipulated Date of Completion /
Likely Date of Completion April 20 2013
Likely Date of Completion April 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,523,900.00
Awarded for
₹ 1,447,436.09
Project highlights
Fabrication and supply of metal cages of size 1.37 m X 1.40 m X 1.22 m.
Contractors
M/s. Rakesh Kambli
Consultants
In-house (GSIDC)