Project Duration
Stipulated Date of Commencement
September 24 2006
Stipulated Date of Completion /
Likely Date of Completion September 23 2007
Likely Date of Completion September 23 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,659,445.00
Awarded for
₹ 5,977,351.00
Project highlights
Extension work of school building
Contractors
M/s. M.B. Kinlekar, M/s. M.B. Kinlekar
Consultants
M/s. Effective Architectural Services
Sub Works
This project involved 1 sub works. The details of the same available below
1
Extension of H. B. Desai Government High School at Thane in Sattari Taluka – Additional work of 4 classrooms, laboratory, compound wall, store room & hall.
100% completed
Project Duration
Stipulated Date of Commencement
December 18 2009
Stipulated Date of Completion /
Likely Date of Completion February 17 2011
Likely Date of Completion February 17 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,376,099.00
Awarded for
₹ 8,679,690.00
Project highlights
Construction of additional 4 classrooms, laboratory, compound wall, store room, hall along with painting and electrification works.
Contractors
M/s. K. G. Thomas
Consultants
M/s. Effective Architectural Services
See Similar Projects
Infrastructure works for Sanjay Centre for Special Education at Porvorim
View Project
Construction of Higher Secondary School building for Dr.K.B.Hedgewar Higher Secondary School at Cujira, Bambolim,Tiswadi,Goa.
View Project
Repairs/Upgradation & maintenance of Government Schools in State of Goa – Civil, Plumbing & Electrical works – Package G (Quepem Taluka) – GPS Corla, GPMS Kanibag
View Project