Project Duration
Stipulated Date of Commencement January 29 2016
Stipulated Date of Completion /
Likely Date of Completion
March 29 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,420,872.31
Awarded for ₹ 4,171,191.00

Project highlights

The scope of works includes electrical work

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Rahul Deshpande Associates
 
Similar Projects

See Similar Projects

Similar Project

Interior work for TCP branch office, Tiswadi Branch, 5th Floor, Kamat Towers

View Project
Similar Project

Telephone Exchange and UPS (Part A- UPS work)

View Project
Similar Project

Extension of Secretariat Building, Porvorim- Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.