Project Duration
Stipulated Date of Commencement
November 13 2010
Stipulated Date of Completion /
Likely Date of Completion December 11 2011
Likely Date of Completion December 11 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,016,915.00
Awarded for
₹ 11,962,654.36
Contractors
M/s.Sunshine Electric Co. Pvt. Ltd.
Consultants
M/s. Effective Architectural Services