Project Duration
Stipulated Date of Commencement October 28 2014
Stipulated Date of Completion /
Likely Date of Completion
November 27 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 45,817,308.00
Awarded for ₹ 49,506,270.40

Project highlights

Conversion of electrical overhead lines to underground cables.

 
Gallery Image
Contractors
M/s. Nanu Engineers Pvt. Ltd.,
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Bridge connecting Veluz and Dhabos in Valpoi including approaches.

View Project
Similar Project

Construction of Minor Bridge across river Tar at Mapusa, Goa on MDR-14

View Project
Similar Project

Improvement / Hot mixing of roads in Arpora – Candolim.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.