Project Duration
Stipulated Date of Commencement
December 11 2014
Stipulated Date of Completion /
Likely Date of Completion December 31 2014
Likely Date of Completion December 31 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,055,616.00
Awarded for
₹ 55,882,025.78
Project highlights
Development of service road and site development at Mont Boa Vista which includes surface excavation ,laying of 40mm thick BM,25mm thick Asphalt Concrete , Providing and laying of BMC ,laterite masonary etc.
Contractors
M/s.Jagdish Pai
Consultants
M/s.Manguesh Prabhugaonkar