Project Duration
Stipulated Date of Commencement
March 06 2009
Stipulated Date of Completion /
Likely Date of Completion March 05 2011
Likely Date of Completion March 05 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 95,341,851.00
Awarded for
₹ 142,499,999.00
Project highlights
(1) Length of Bridge is 125.05 mts and 12 mtr wide.
(2) 48.70 m x 25 pans PSC cast in Suitu Box Girder Spans.
(3) 25.65 mts PSC ‘T’ Beam Girder & Deck slab.
Contractors
M/s. Banka Consultants.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.