Project Duration
Stipulated Date of Commencement
February 26 2011
Stipulated Date of Completion /
Likely Date of Completion June 25 2011
Likely Date of Completion June 25 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,157,295.00
Awarded for
₹ 8,469,740.00
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
In-house (GSIDC)