Project Duration
Stipulated Date of Commencement April 15 2004
Stipulated Date of Completion /
Likely Date of Completion
March 14 2005
Status
100%
Completed
Cost (₹)
Estimated at ₹ 424.45 lakh
Awarded for ₹ 42,350,000.00

Project highlights

Design and Construction of bridge across river Mapusa connecting Corjuem and Poira including approaches

 
Gallery Image
Contractors
M/s. S.N.Bhobe & Associates Pvt. Ltd
Gallery Image
Consultants
M/s. TPF Engineering Pvt. Ltd (M/s. S.N.Bhobe & Associates Pvt. Ltd)
 
Similar Projects

See Similar Projects

Similar Project

Widening of road in Calangute – Baga – Electrical works..

View Project
Similar Project

Improvement and Upgradation of the road from Borim Bridge Junction to Kamaxi Temple and Shivnath Temple in Shiroda Constituency.

View Project
Similar Project

Conversion of Overhead Lines to underground system and installation of 11KV & LT equipment’s along the road from NIO circle to Dona Paula Jetty and NIO circle to Rajbhavan road

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.