Project Duration
Stipulated Date of Commencement January 09 2015
Stipulated Date of Completion /
Likely Date of Completion
February 08 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 884,746.00
Awarded for ₹ 885,000.00

Project highlights

Demolition of existing deteriorated jetty.

 
Gallery Image
Contractors
M/s. Kamat Equipments Services
Gallery Image
Consultants
M/s. Kashec Engineers Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Widening & Strengthening of the existing road from Old Goa Junction to Gaundali Bridge approach including asphalting from Old-Goa Junction to Khandola College

View Project
Similar Project

Construction of approaches to Cumbarjua bridge including road link upto Khandola college.

View Project
Similar Project

Improvement and Upgradation of road network at Piligao, Curti, Ponda Town and Chodan.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.