Project Duration
Stipulated Date of Commencement
January 09 2023
Stipulated Date of Completion /
Likely Date of Completion January 17 2023
Likely Date of Completion January 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,640,591.00
Awarded for
₹ 921,000.00
Contractors
M/s. Harish Iron Store
Consultants
M/s. Ameet Sukhthankar Architects & Interior Designers.
See Similar Projects
Repairs/Upgradation & Maintenance Of Government Schools In The State Of Goa – Civil, Plumbing & Electrical Works – Package-I (Pernem Taluka) – Rate Contract
View Project
Repairs/Upgradation and Maintenance of Govt. Schools in the state of Goa – Civil, Plumbing and Electrical works -Bicholim Taluka- Package B-(G.P.S. Amona, G.P.S. Digne Surla, G.P.S. Kharwada Amona, G.P.S. Maini Navelim, G.P.S. Nawarwada Pale, G.P.S. Rumad Surla, G.P.S.Khodgini Surla, G.P.S. Khajan Surla )