Project Duration
Stipulated Date of Commencement
June 15 2018
Stipulated Date of Completion /
Likely Date of Completion June 30 2018
Likely Date of Completion June 30 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,204.00
Awarded for
₹ 45,312.00
Project highlights
The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Design and construction of bridge over river Satrem at Satrem, Sattari Taluka.
View Project
Construction of Pedestrian pathway on existing approach to road over bridge at Rawanfond Margao Goa
View Project
Design and Construction of Bridge across River Mandovi at Panaji including approaches on NH 17 between Pundalik Nagar Junction (Porvorim) and Merces Junction
View Project





