Project Duration
Stipulated Date of Commencement
November 25 2013
Stipulated Date of Completion /
Likely Date of Completion January 08 2014
Likely Date of Completion January 08 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,119,955.00
Awarded for
₹ 3,333,897.00
Project highlights
AV work
Contractors
M/s. Unify Enterprise Communications Pvt. Ltd.
Consultants
In-house (GSIDC)