Project Duration
Stipulated Date of Commencement
May 01 2008
Stipulated Date of Completion /
Likely Date of Completion June 29 2008
Likely Date of Completion June 29 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,660,434.00
Awarded for
₹ 8,378,990.00
Contractors
M/s. Concept Creators
Consultants
Frischmann Prabhu India (I) Pvt Ltd.