Project Duration
Stipulated Date of Commencement
May 16 2014
Stipulated Date of Completion /
Likely Date of Completion June 15 2014
Likely Date of Completion June 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 445,576.00
Awarded for
₹ 521,000.00
Project highlights
Electrical Works
Contractors
M/s.Desai Electrical & Electronics Sales & Services
Consultants
In-house (GSIDC)