Project Duration
Stipulated Date of Commencement
March 27 2007
Stipulated Date of Completion /
Likely Date of Completion March 26 2008
Likely Date of Completion March 26 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 54,371,959.00
Awarded for
₹ 69,139,000.00
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of Swimming pool at Ponda Sports Complex – Additional works such as Jogging Track, Road, Compound wall, Security Cabin etc.
100% completed
Project Duration
Stipulated Date of Commencement
February 12 2009
Stipulated Date of Completion /
Likely Date of Completion May 11 2009
Likely Date of Completion May 11 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,71,379.00
Awarded for
₹ 47,00,750.52
Contractors
M/s. Rohit Equipments
Consultants
M/s. Datta Kare Associates
See Similar Projects
Repairs & Upgradation of Govt High schools in the state of Goa-Canacona Taluka (Package A)
View Project
Construction of Government High School at Bhuipal in Sattari Taluka.
View Project
Extension to middle school at Shristhal Canacona.
View Project