Project Duration
Stipulated Date of Commencement
March 02 2020
Stipulated Date of Completion /
Likely Date of Completion December 30 2023
Likely Date of Completion December 30 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 76,417,045.00
Awarded for
₹ 78,601,439.00
Project highlights
Construction of memorial of Shri. Manohar Parrikar with dhyan kutir, library, water body and landscaping work all around.
Contractors
M/s. Univastu India Ltd.
Consultants
M/s UCJ Architecture & Environment