Project Duration
Stipulated Date of Commencement January 05 2022
Stipulated Date of Completion /
Likely Date of Completion
January 14 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 25,108,748.16
Awarded for ₹ 28,284,599.49

Project highlights

Construction of sewage Treatment Plant

 
Gallery Image
Contractors
M/s.Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. FP Project Management.
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of Primary Health Centre at Shiroda, Goa – Operation Theatre Works.

View Project
Similar Project

Supply Installation Testing & Commissioning of Bio Medical Equipment (Part III) CT Scan.

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Repair of Chilled Water Type Cassette Units installed in OPDs and an AHU installed for an Operation Theatre at Sub District Hospital, Ponda Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.