Project Duration
Stipulated Date of Commencement
January 05 2022
Stipulated Date of Completion /
Likely Date of Completion January 14 2023
Likely Date of Completion January 14 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 25,108,748.16
Awarded for
₹ 28,284,599.49
Project highlights
Construction of sewage Treatment Plant
Contractors
M/s.Indage Development Construction Pvt. Ltd.
Consultants
M/s. FP Project Management.