Project Duration
Stipulated Date of Commencement
February 28 2014
Stipulated Date of Completion /
Likely Date of Completion April 27 2014
Likely Date of Completion April 27 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,216,737.00
Awarded for
₹ 3,626,240.00
Project highlights
The scope of work involves supply and installation of Tranformer and DG Set.
Contractors
M/s.Arken Solutions Pvt. Ltd.
Consultants
In-house (GSIDC)