Project Duration
Stipulated Date of Commencement
March 07 2019
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 26,061,707.00
Awarded for
₹ 29,232,085.61
Project highlights
Seed processing & Storage Building
Contractors
M/s. Kamat Equipment Services
Consultants
M/s. Creative Abode