Project Duration
Stipulated Date of Commencement
March 04 2014
Stipulated Date of Completion /
Likely Date of Completion December 05 2014
Likely Date of Completion December 05 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,010,124.72
Awarded for
₹ 20,631,076.32
Project highlights
New community hall to cater to needs of the local villagers to hold functions and gatherings personal / public
Contractors
M/s. Prabhudesai & Associates,
Consultants
M/s. Murty & Manyam,