Project Duration
Stipulated Date of Commencement
November 05 2014
Stipulated Date of Completion /
Likely Date of Completion November 04 2015
Likely Date of Completion November 04 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 83,050,730.62
Awarded for
₹ 113,551,965.00
Project highlights
hall with 300 capapcity for conducting socio-cultural events with provision of Anganwadi at various location in Canacona taluka
Contractors
M/s. Shalaka Infra-Tech Pvt. Ltd
Consultants
M/s. Murty & Manyam Architects & Engineers