Project Duration
Stipulated Date of Commencement
February 10 2024
Stipulated Date of Completion /
Likely Date of Completion August 09 2024
Likely Date of Completion August 09 2024
Status
50%
Completed
Cost (₹)
Estimated at
₹ 8,374,398.24
Awarded for
₹ 6,992,632.42
Project highlights
Furniture works
Contractors
M/s. Aai Jee Interiors
Consultants
M/s. Rahul Deshpande & Associates