Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion June 20 2013
Likely Date of Completion June 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,532,155.00
Awarded for
₹ 14,482,150.00
Project highlights
Stage lighting work for the project
Contractors
M/s. Modern Stage Services
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.