Project Duration
Stipulated Date of Commencement
February 24 2010
Stipulated Date of Completion /
Likely Date of Completion August 23 2010
Likely Date of Completion August 23 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,364,774.00
Awarded for
₹ 6,037,795.00
Project highlights
Fire fighting work for the project
Contractors
M/s. Consolidated Construction Consortium Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.