Project Duration
Stipulated Date of Commencement
September 04 2009
Stipulated Date of Completion /
Likely Date of Completion March 03 2010
Likely Date of Completion March 03 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,245,405.00
Awarded for
₹ 23,666,666.00
Project highlights
External Electrical work for the project
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Construction of Panhayat Ghar at V.P.Caurem-Pirla
View Project
Civil, Plumbing & Electrical works (Balance).
View Project
Construction of Joggers Park at Chicalim.
View Project





