Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion October 18 2010
Likely Date of Completion October 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,680,288.00
Awarded for
₹ 46,380,920.00
Contractors
M/s. Indecor Slides (I) Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Additional electrical work.
View Project
Construction of Ravindra Bhavan at Sanquelim, Goa-Phase I :Civil, Plumbing, Land development, Electrical
View Project
Construction of Panchayat Ghar along with Community Hall at V.P.Ugem
View Project