Project Duration
Stipulated Date of Commencement
August 24 2023
Stipulated Date of Completion /
Likely Date of Completion July 27 2024
Likely Date of Completion July 27 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 21,027,260.00
Awarded for
₹ 18,149,769.44
Project highlights
Interior and furniture including signages murals etc.
Contractors
M/s. Virender Kumar & Co.
Consultants
M/s. UCJ Architecture & Environment