Project Duration
Stipulated Date of Commencement
March 25 2021
Stipulated Date of Completion /
Likely Date of Completion April 08 2021
Likely Date of Completion April 08 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,062.00
Awarded for
₹ 52,465.00
Project highlights
The scope of work includes Supply, Installation, Testing & Commissioning of 200 A Distribution BOX. for obtaining electricity connection to PHC Navelim.
Contractors
M/s. Consistent Engineers
Consultants
In-house (GSIDC)
See Similar Projects
Medical gas and Vacuum System work
View Project
Lift work
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa
View Project