Project Duration
Stipulated Date of Commencement
August 26 2016
Stipulated Date of Completion /
Likely Date of Completion November 25 2017
Likely Date of Completion November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,051,673.00
Awarded for
₹ 14,133,458.98
Project highlights
(1) Ground floor consists of 1 nos. of shop of size 2.35 x 4.54.mt
(2) First floor consists of Panchayat Office, seperate Talathis Office, Sarpanch , Secretary and Conference room, Animal Husbandary & Electricity Dept and seperate toilets.
Contractors
M/s.Vaishnavi Infrastructure
Consultants
M/s. Creative Abode