Project Duration
Stipulated Date of Commencement
January 17 2022
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 10,824,992.64
Awarded for
₹ 9,125,700.00
Project highlights
Hospital furniture works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. KICONS Limited