Project Duration
Stipulated Date of Commencement
August 26 2013
Stipulated Date of Completion /
Likely Date of Completion April 25 2014
Likely Date of Completion April 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,996,583.00
Awarded for
₹ 36,599,357.37
Project highlights
Upgraded premises of the old premises of CHC Tuem.
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. KICONS Limited