Project Duration
Stipulated Date of Commencement
November 06 2022
Stipulated Date of Completion /
Likely Date of Completion December 31 2023
Likely Date of Completion December 31 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,138,926.09
Awarded for
₹ 25,393,644.83
Project highlights
The centralised substation will cater to all the building blocks in the campus with proper distribution of power using switch gears.
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. FP Project Management
See Similar Projects
Civil works
View Project
Minor maintenance and renovation works at Goa Dental College and Hospital, Bambollim,Goa.
View Project
Upgradation work at GMC, Bambolim – UPS system for modular OTs.
View Project





