Project Duration
Stipulated Date of Commencement
March 10 2014
Stipulated Date of Completion /
Likely Date of Completion May 09 2014
Likely Date of Completion May 09 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,069,411.00
Awarded for
₹ 2,895,049.87
Project highlights
Supply, Installation, Testing & Commissioning of Audio Visual equipments
Contractors
M/s. HiTech Audio systems Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.