Project Duration
Stipulated Date of Commencement
March 05 2024
Stipulated Date of Completion /
Likely Date of Completion December 04 2024
Likely Date of Completion December 04 2024
Status
25%
Completed
Cost (₹)
Estimated at
₹ 17,043,187.00
Awarded for
₹ 16,781,944.68
Project highlights
Construction of Community hall for Tribal community for conducting social and cultural activities.
Contractors
M/s. Sri Srinath Infra
Consultants
Ms Murty & Manyam