Project Duration
Stipulated Date of Commencement
December 08 2022
Stipulated Date of Completion /
Likely Date of Completion August 31 2024
Likely Date of Completion August 31 2024
Status
94%
Completed
Cost (₹)
Estimated at
₹ 11,487,470.47
Awarded for
₹ 15,540,162.00
Project highlights
Construction of community hall for tribal community for conducting social and cultural activities.
Contractors
M/s Concept Creator
Consultants
Ms Murty & Manyam