Project Duration
Stipulated Date of Commencement September 02 2023
Stipulated Date of Completion /
Likely Date of Completion
August 31 2024
Status
92%
Completed
Cost (₹)
Estimated at ₹ 8,067,062.00
Awarded for ₹ 6,960,664.46

Project highlights

It includes loose furniture, carpentary furniture, false ceiling, ACP Cladding etc

 
Gallery Image
Contractors
M/s. Concept Creator
Gallery Image
Consultants
M/s. Shiva Consultancy Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation of Building of Directorate of Higher Education at Porvorim-Goa – Balance – Civil, Plumbing and Fire Fighting work

View Project
Similar Project

Improving & Revamping of Water supply, Power supply & Sewerage Netwoirk at Goa Medical College & Hospital, Bambolim-Goa – Phase II – SH – Revamping of Existing Fire fighting Grid at GMC, Bambolim-Goa.

View Project
Similar Project

Construction of New District & Sessions Court Complex at Merces, Tiswadi – Goa: Balance Electrical works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.