Project Duration
Stipulated Date of Commencement
August 14 2016
Stipulated Date of Completion /
Likely Date of Completion November 13 2017
Likely Date of Completion November 13 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,168,164.07
Awarded for
₹ 15,901,572.33
Project highlights
Lower Ground Floor and Ground Floor: 11 shops &
First Floor: Hall along with dining
Contractors
M/s. Satish R. Lal
Consultants
M/s. Bhaskar Wagle & Associates