Project Duration
Stipulated Date of Commencement
March 04 2007
Stipulated Date of Completion /
Likely Date of Completion July 03 2007
Likely Date of Completion July 03 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,110,745.00
Awarded for
₹ 5,686,390.00
Project highlights
Land filling and construction of retaining wall
Contractors
M/s. Madanant Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
See Similar Projects
Construction of Multipurpose Hall and Office Building for V.P.Salvador Do Mundo – Additional works.
View Project
Extension of temporary jetty near Kala Academy.
View Project
Beautification of Valpoi Town.
View Project





