Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion June 25 2008
Likely Date of Completion June 25 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 67,853,010.52
Awarded for
₹ 73,566,292.00
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.