Project Duration
Stipulated Date of Commencement
December 21 2015
Stipulated Date of Completion /
Likely Date of Completion April 20 2016
Likely Date of Completion April 20 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,709,441.00
Awarded for
₹ 11,818,492.26
Project highlights
Ella & Margao: 1. Total area of the premises: 206.00sq.m.
2. Laboratory comprises of Cabin, office, Dark Chemical Storage Room, Main Hall, Preparation/Drying Room, Soil Storage Room, Research Room and Toilets.
3. Vitrified flooring for the cabin & office space and Kotah Flooring for main hall and other storage rooms.
4. Granite counter, soil storage racks and ramp upto soil storage room for the vehicle.
Contractors
M/s. Trivikram Constructions
Consultants
M/s. Creative Abode
See Similar Projects
Construction STP Sanquelim – Compound Wall & Allied work.
View Project
Providing 11 kV transformer substation for release of electrical connection to the office premises of at Vasco.
View Project
Major Repairs to Old Aged Home of IPA Provedoria at Chinchinim
View Project