Project Duration
Stipulated Date of Commencement March 08 2019
Stipulated Date of Completion /
Likely Date of Completion
March 07 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 194,696,690.00
Awarded for ₹ 194,177,475.00

Project highlights

The project comprises of a Grand Auditorium – 740 Seater Capacity. Ground Floor consists of a Cafetaria, Pantry, Green rooms for ladies, gents and VIP, Loading & unloading deck, Administration Section, Ticketing & information counter, Store rooms, Toilets for Handicapped, Ladies and Gents etc.First Floor shall comprise of Mini lecture halls, Classrooms – 03nos, Library, Pantry, VIP rest room for ladies and gents, Rehearsal room, Store rooms, AHU rooms – 2nos., Handicapped toilets, ladies & gents toilets etc. Second Floor shall comprise of a Black box – 120 seating capacity, Pantry, Musical Classrooms – 4nos, Toilets for Handicapped, Ladies and Gents, Changing rooms, AHU rooms – 2nos., Store rooms etc.

 
Gallery Image
Contractors
M/s. Narayan Kumar Infrastructure (I) Pvt. Ltd
Gallery Image
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply and laying of 33KV HT cable from Sai service junction to the new High Court Complex and allied electrical works

View Project
Similar Project

Construction of Building for Food & Drugs Administration Block at Bambolim, Goa

View Project
Similar Project

Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim-Goa – Interior & Furniture works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.