Project Duration
Stipulated Date of Commencement
January 24 2014
Stipulated Date of Completion /
Likely Date of Completion July 23 2014
Likely Date of Completion July 23 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 48,097,756.00
Awarded for
₹ 54,788,911.15
Project highlights
· The project includes Construction of Jogger’s Park in a plot of Area 30821 Sqm located at Dabolim, Mormugao Taluka at South Goa District.
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Consultants
M/s. Casta Engineers Pvt. Ltd.