Project Duration
Stipulated Date of Commencement
December 14 2019
Stipulated Date of Completion /
Likely Date of Completion December 13 2020
Likely Date of Completion December 13 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 57,329,858.55
Awarded for
₹ 43,924,239.85
Contractors
M/S.VIPIN SHAH & ASSOCIATES.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Major Maintenance Work of Goa Medical College & Hospital at Bambolim, Goa SH : Operation & maintenance contract for Centralized Air Conditioning (AC) system of GMC at Bambolim, Goa for 3 years (2020-2023)
View Project
Design, supply, erection, testing and commissioning of 5 Nos. pre-fabricated Modular Operation Theatres along with centralised medical gas pipe system within the 5 No. OTs at Goa Medical College & Hospital, Bambolim, Goa
View Project
External electrical work at area around new Library Building and Power supply to new Library Building, GMC Complex, Bambolim, Goa – Supply, laying of 1100 V power supply cable.
View Project